Case Study 5 - Client: WeLink Communications UK

Project Overview

DMB Engineering partnered with WeLink Communications UK to pioneer Britain's first major wireless gigabit broadband service in Edinburgh. The project aimed to deliver lightning-fast internet speeds to both the Old and New Towns while preserving the historical integrity of the World Heritage Site, eliminating the need for disruptive street excavations.

Picture 1.jpg

Challenges:

The project faced significant challenges:

 

Innovative Infrastructure Deployment:

Implementing wireless gigabit broadband without conventional street excavations in a historically sensitive area.

Utilizing existing wifi AP for enhanced efficiency and reduced disruption.

 

Residential Proximity:

Executing works near residential homes with meticulous care to minimize disruptions and ensure safety.

Solution:

DMB Engineering's team, on-site since early in the year, executed a comprehensive set of works:

Cable Running/Pulling:

Efficient execution of cable running and pulling to establish the wireless gigabit broadband infrastructure.

 

MEWP Works:

Implementation of Mobile Elevated Work Platforms (MEWP) for elevated works, ensuring safety and efficiency.

 

Rack Installations and Electrical Connection:

Strategic placement of racks for equipment and ensuring electrical connections for seamless operations.

Care and Precautions:

Care and Precautions:

Given the proximity to residential areas, the engineering team implemented a series of precautions:

 

Barrier Installation:

Clear barriers were erected, and pedestrian traffic was rerouted to maintain safety.

 

Noise Control:

Commitment to minimizing noise pollution by avoiding loud works before 9 am or after 4 pm.

Benefits:

With the successful completion of the installation, several key benefits were realized:

 

Increased Coverage Capacity:

The ability to further increase coverage, enhancing the reach of high-speed broadband services.

 

Ultra-Fast Broadband Options:

Residents within the covered area can now select from ultra-fast broadband options, including speeds of up to 1gbps.

Conclusion:

Conclusion:

DMB Engineering's collaboration with WeLink Communications UK successfully addressed the challenges of deploying wireless gigabit broadband in a historically significant area. By efficiently managing line of sight and network issues and prioritizing residential considerations, the project achieved a significant milestone in delivering cutting-edge broadband services to Edinburgh's Old and New Towns.

Next Steps:

The success of this project sets the stage for continued collaboration between DMB Engineering and WeLink Communications UK, paving the way for the exploration of additional opportunities to expand high-speed broadband services in other regions and refine wireless gigabit broadband infrastructure.